NRSM, INC. sports construction crews have over thirty-five years of experience in the tennis industry. We manufacturer and use the finest sports coating material in the country. Our Acrytech Colorguard (with UV-15 protection) as well as our high tech Acrytech Sports Resurfacer will make any sports court be the talk of the town. Which accounts for about 95% of all our sports court projects. We are also an authorized supplier for two other national sports coating brands (Nova Sports & Laykold) if your project specifies either of these manufacturers. Please Contact us for more details.
Our professional construction and resurfacing crews focus on projects in North Carolina, South Carolina, Georgia, Tennessee and Florida. With also have partnership with other court builders and general contractors in other parts of the country to make sure we cover a wider range of customers.
New Construction (General Process Guidelines)
General Layout of the over-all project site including the sports courts.
(Usually owner or general contractor provided)
Rough & Fine Grading
Compaction of 95% with certified paperwork required
Proper 1% Slope all in one direction is required
(Usually owner or general contractor provided)
Installation of 4 to 5 inches of stone or mixed coquina commerical base material.
With 1 ½ to 2 inches of Premium Sports Asphalt applied to the above base material
Optional Leveling Course can be added of 1 to 1 1/2 on top of the other asphalt finish.
Fine tuning the edges with saw cutting for a professional finish look.
The normal CURE PERIOD is 14 to 30 days depending on the weather.
Landscaping and irrigation
Delivery and Installation of Sports Lights
Lights and Landscaping needs to be pretty much finished beforehand
Sports Fencing can start as early as the 14th to 30th day of the paving being installed.
And depending on the other work listed above being completed beforehand.
Net Footer Foundations can be installed at this point in the project.
General Pressurewash and Cleaning of the Asphalt
Checking & Marking for Low Spots.
USTA Requirements that water can’t cover over the height of quarter 1 hour
(after rain or flooding) and at least 70 degrees for a walk through test.
Patch low spots with our Sports Patch Material.
Apply 1 to 2 coats of Sports Resurfacer
Apply 2 to 4 Color-Coat Coatings
Stripe the lines
Set the post and hang the nets.
Windscreens and Seating can be added at for additional cost.
Hard Courts are usually consider as all-weather courts and are low
in maintenance and only require daily care due to inclement weather conditions.
Hard Courts maybe left open all year long, therefore extending the
playing season during favorable weather conditions.
Hard Court general speed of the surface can be adjusted (at time of applying coatings)
To the general speed that the owner wants to achieve. This is done by adding or
sub-tracting the natural sand base.
Hard Courts (concrete or asphalt) can be used for construction,
reconstruction and resurfacing of the following sports court applications:
On average, an asphalt or concrete sports court can be expected to last approximately 15 to 20 years. However, as courts get older, the cracks tend to worsen exponentially and resurfacing becomes more frequent. If this sounds familiar, you should probably be considering a reconstructed court.
NRSM, INC. offers three types of Re-Construction Process:
Over-lay
Provide a layer 1 to 2 inches of new premium sports asphalt topping over the entire court surface. Recommended with sports courts with good sub-bases and minimal structional cracking.
Bucksport, SC
(Before Work Started)
Bucksport, SC
(Demo of Fence Material & Before Surface Prep)
Bucksport, SC
(Demo Fence Material & BB Goals)
Bucksport, SC
(Overlay Completed)
Bucksport, SC
(Finished Fence Work)
Bucksport, SC
(Overlay, Fence and Resurfacing Completed)
Petro Matting
Recommended for courts that fiberglass and recoating repairs have not been successful. Petro mat (usually in 12ft rolls) will be applied before the new asphalt is applied. Paving will take place with either 1 1/2 to 2 inches of Premium Sports Asphalt Then full resurfacing and color coating process will take place to put our professional finishing touches to the project.
Removal of entire existing court(s). This is recommended for courts with depressed areas, structural cracking and other sub-base issues.
Deercreek HOA
(Demo of Courts)
Deercreek HOA
(Demo of Courts & Fence)
Deercreek HOA
(Fine Grade & Install Sub-base)
Deercreek HOA
(Paving)
Deercreek HOA
(Paving)
Deercreek HOA
(Finished Project)
NRSM, INC will provide you with a professional unbiased recommendation as to the best approach to reconstruct your tens courts. We can also provide you with an independent engineering firm to core into the asphalt or concrete (sub-base) and provide a written recommendation as to which approach might meet your specific needs.
________________________________
Color-Coat Chart
Acrytech Colorguard with UV-15 Protection
Colors are as accurate as possible. Slight variations may occur due to site conditions, mixing proportions, installation methods and color clarity on your personal or office computer monitors. For the purest, sharpest and longest lasting sports coatings in the business, your choice should be our Acrytech brand.